Yuleba Surat Road Upgrade
Client: Maranoa Regional Council
Location: Surat, Queensland
Value: $9.80M
Duration: December 2025 - June 2026
The scope of works included:35,000
labour and plant hours
60t
of rock protection
80,500t
placement of pavement material
400m³
of concrete placement
Project OverviewIn late 2025, Suffcon was engaged by Council to deliver the Yuleba Surat Road Upgrade construction project. Located approximately 20 kilometres north of Surat, Queensland, the project involved the upgrade of a 8.8 kilometre stretch of road network, incorporating a combination of greenfield and brownfield works.
Drawing on our team’s extensive experience, Suffcon worked collaboratively with Council’s Project Team to refine the road design and material supply approach, achieving a practical balance between cost efficiency and overall design performance.
The project highlights Suffcon’s capability to deliver innovative, environmentally conscious infrastructure solutions, combining technical expertise with practical delivery to support the long-term sustainability of regional industries.
ServicesProject Management
Bulk earthworks
Pavement material production/crushing
Bulk haulage
Road pavement construction
Bitumen sealing