Flood Recovery Works

Client: Maranoa Regional Council

Location: Maranoa Region, Qld

Value: $9.15M

Duration: October 2023 - September 2024

The scope of 
works included:

8,497

damage sites addressed

344

roads in the region

99,000t

of material sourced

Project Overview

Suffcon was engaged by the Maranoa Regional Council to deliver the 2022 Flood Recovery Works — a major infrastructure restoration initiative that addressed 8,497 damage sites across 344 roads in the region.

The project required a strategic and highly coordinated approach to material logistics and resource management. It involved the handling of approximately 99,000 tonnes of material sourced form a combination of council-sourced gravel pits and commercial quarries.
Through effective coordination and a strong focus on execution, Suffcon successfully completed the project, restoring essential road infrastructure and enhancing the resilience of the Maranoa region's transport network.

Services
  • Project Management

  • Material Logistics & Haulage

  • Rural Road Maintenance

  • Road Construction